Weekly production schedule — Locked & Visible updates (rolling 8 weeks)

Locked (Upcoming)

290K

cans confirmed

Visible (Planned)

282K

cans pending confirmation

Requested

66K

awaiting MSI slot

Avg OEE (3-wk)

84%

vs 85% target

Open Blockers

6

need resolution

LOCKEDVISIBLEREQUESTEDCOMPLETED

Production Runs

SKUQuantityCasesStatusNotes
MA-651,750575LOCKEDRunning Mon-Wed
MT-641,400460LOCKEDRunning Thu-Fri
Cappuccino-620,700230LOCKEDRunning Fri (partial)
OEE Target: 85%

Updates

MA-6 started Monday AM on schedule
MT-6 prepped, raw materials staged
Cappuccino-6 may push to Mon WK13 if MT-6 runs long

Blockers

Watching Cappuccino-6 timing — may slip to next week
Source: John confirmed schedule 3/15. Grady providing daily updates.

Data Sources

Locked: Confirmed production schedule from MSI Express via John/Grady. Updated weekly (typically Friday for following week).

Visible: Planned production from Sesh supply plan, shared with MSI but not yet confirmed.

Requested: Submitted to MSI, awaiting capacity confirmation.

OEE: MSI Express daily production reports, aggregated weekly. Target: 85%.

MSI Express Production ReportsJohn/Grady weekly syncSesh Supply Plan